Project Name

Contractor Name

Contract Date

Contract Number

Physical Progress

Initial Project Estimate

Bushehr Sewage Collection Network Project in the Historic Fabric Area - Part 2 (Shanbedi, Dehdashti and part of Kooti Neighborhoods)    

Granit Saze Markazi Co.

97/07/22

2040

100%

81,189,307,470

Station Site Development ( L ) and Construction of Warehouse Shed

Pas Karaneh

98/05/07

2048

85%

53,578,301,157

Bushehr Wastewater Treatment Plant Upgrade Project

Pishtazan Bardin Co.

98/04/31

2045

95%

91,916,880,964

Construction of Pumping Station PSH of Genaveh City

Farbal Bana Co.

1398/01/06

2097

46%

47,859,561,590

Genaveh Wastewater Treatment Plant Effluent Channel Construction Project

Pas Karaneh Co.

1398/05/07

2069

85%

103,287,935,733

Construction of Sewage Network Zone H of Genaveh City and Its Scattered Lines

Zarngar Shiraz Co.

1400/05/12

2154

30%

262,687,046,803

Construction of Sewage Network Zone G of Deylam City and Its Scattered Lines

Mehrab Pars Co.

1401/05/12

2153

40%

193,421,706,829