Status of Active Water Projects in Bushehr Province

 




County

Project Name

Physical Progress (٪)

Length (meters)

Contract Date

Contract Duration (months)

Funding Source

Current Status: Active/Inactive



Dashtestan

Construction of 10,000 m³ Reservoir in Shabankareh

71.5

---

97/06/27

12

 

Active



Execution of Water Transmission Line and 1,000 m³ Reservoir in Kalameh

10

-

99/07/30

12

 

Active



Tangestan

Completion of 5,000 m³ Reservoir in Delvar

39

---

99/01/30

12

 

Active



1,000 m³ Reservoir in Boneh Gaz

21

---

98/05/02

18

National

Active



Dashti

500 m³ Reservoir in Chavoshi Village

90

---

98/11/06

9

National

Active



Second Priority: Water Transmission Line from Tang-e Sedr Wells to Dashti County

45

5300

99/04/23

18

 

Active



500 m³ Reservoir in Golestan Village

86

---

98/11/05

6

National

Active



Kangan

Construction of 500 m³ Reservoir and Water Transmission Line in Bagh Sheikh Village, Siraf

5

-

1400/12/11

12

 

Active



 

Execution of Transmission Line from Kangan Reservoir to Bank Reservoir

0

-

1400/12/11

12

 

Active



Deylam

Execution of Water Transmission Line for Deylam City

0

0

1400/12/02

12

Cities with Water Stress - Rural Nomadic

Active



Deprivation Elimination Projects

Drinking Water Supply to 39 Villages of Bushehr Province

2

500

1400/10/05

30

 

Active



Dashtestan and Dashti

Execution of Bottom-Hole Cleaning and Pumping Test of Hand and Deep Drinking Water Wells in Dashtestan and Dashti Counties

8

0

1401 

 

 

Active



Province

Execution of Intake Structure and Water Transmission Canal for Boushigan Water Treatment Plant, Bushehr Province

65

 

1401 

 

 

Active